INSPECTION REPORT

PROJECT: XYZ New Building

  FIELD REPORT NO: CC-075 

CONTRACT: XYZ  Corporation 

PROJECT#: PCC-007612 

DATE: 6/12/03 TIME: 11:45AM  WEATHER: Mild TEMP RANGE: 65-75 F 
WORK IN PROGRESS: PRESENT AT SITE:
Interior Drywall 5 EC
Exterior Trim & Weatherproofing 4 MC
HVAC Fitting & Controls 3 GC
6 PC
OBSERVATION KEY- Progress Reported Discrepancy Problem Alert
ICON

    OBSERVATIONS

1. Caulking for exterior joints not adhering. Product being applied out of spec (low temp, rain. )
2. Mechanical Room, Admin Building - OSHA violations due to contractor failure to maintain space. 
3. Sill plate detached at southwest corner.
4. Spare well casings not capped. 
5. Electrical Room, Arts Building - Improper fire-stop at removed ventilation points. 
6. HVAC Room, Dining Facility -- Control upgrades complete and functional.
7. Engineering, Building Automation System - System complete and on-line. 
8. Elevator cabs arrived; stored in maintenance garage.
ACTIONS REQUIRED:

None

ITEMS TO VERIFY:

None

ACTIVITY REPORT:
1. Met with GC concerning schedule of Phase II.
2. Reviewed Electrical Spec for Labs with Rep from Smith Electric.
3. Met with Building Inspector concerning asbestos abatment in Lab Building.

REPORT BY: Liebman Associate 21

 Page 1 of 1 Pages