INSPECTION REPORT |
| PROJECT:
XYZ New Building |
FIELD REPORT NO: CC-075 |
| CONTRACT:
XYZ Corporation |
PROJECT#: PCC-007612 |
| DATE:
6/12/03 |
TIME:
11:45AM |
WEATHER:
Mild |
TEMP RANGE: 65-75 F |
| WORK IN
PROGRESS: |
PRESENT AT SITE: |
| Interior Drywall |
5 EC |
| Exterior Trim & Weatherproofing |
4 MC |
| HVAC Fitting & Controls |
3 GC |
|
6 PC |
OBSERVATION
KEY- Progress Reported
Discrepancy Problem Alert |
|
|
ICON |
OBSERVATIONS |
|
|
 |
1.
Caulking for exterior joints not adhering. Product being applied out
of spec (low temp, rain. ) |
|
|
 |
2.
Mechanical Room, Admin Building - OSHA violations due to contractor
failure to maintain space. |
|
|
 |
3. Sill plate detached at southwest corner. |
|
|
 |
4. Spare well casings not capped. |
|
|
 |
5. Electrical Room, Arts Building
- Improper fire-stop at removed ventilation points. |
|
|
 |
6. HVAC Room, Dining Facility -- Control upgrades complete and functional. |
|
|
 |
7. Engineering,
Building Automation System - System complete and on-line. |
|
|
 |
8. Elevator cabs arrived; stored in maintenance garage. |
| ACTIONS REQUIRED: |
|
|
|
|
None |
|
|
| ITEMS TO VERIFY: |
|
|
|
|
None |
|
|
| ACTIVITY REPORT: |
|
|
1. Met with GC concerning schedule of Phase II. |
|
2. Reviewed Electrical Spec for Labs with Rep from Smith Electric. |
|
3. Met with Building Inspector concerning asbestos
abatment in Lab Building. |